Works from Monday 14th April 2003

---------------------------------
Roadworks Logo A38 Star. Between Rowberrow Lane and the County Boundary.

Installation of crash barrier completed. Contractor will be returning to site to provide access onto public footpath for one week. Traffic management will only be in place outside of peak flows 9.30 to 15.30.

Roadworks Logo B3139 Blackford Road, Mark, B3139 Pilcorn Street and Latcham, Wedmore, B3139 Panborough Road, Theale, West Road, Lympsham and Perry Green, Wembdon.

Carriageway patching works in advance of next years surface dressing season. Traffic light control on B3139.

Roadworks Logo   Fairfax Road/Weacombe Road, Bridgwater

Providing dropped crossing facilities.

Roadworks Logo   Watery Lane and Clare Street, North Petherton

Provision of dropped crossing facilities

Roadworks Logo   Broadlands Avenue, North Petherton

Surface water drainage.

Roadworks Logo   Townsend Road, Wedmore

Surface water drainage.

Roadworks Logo  

Chilton Polden Moor Bridge, over South Drain

Bridge strengthening works continue until the end of May 2003. Works are being carried out under a Temporary Road Closure

Roadworks Logo  

Whitehouse Bridge, White House Lane, East Brent

This scheme is progressing well now that the arch is stabilized and a method has been devised for dealing with the river water. The completion date should be around the end of April 2003. An extension of the Temporary Road Closure will be applied for should the completion date slip into early May 2003

Roadworks Logo A361

Greylake Culvert, Moorlinch

Parapet repairs and safety fencing. Works programmed for a further five weeks involving single lane traffic control working

-----------Western Power Distribution--------

 

Nothing to report

-----------Bridge Refurbishment Works--------

Nothing to report

------------TRANSCO---------

   

Nothing to report

----------Wessex Water--------

 

Bridgwater

Main relining works continue in A39 Bath Road. The first phase is working from Cross Rifles roundabout to 167 Bath Road. Single lane traffic control working as works progress over the railway bridge. This phase is programmed for completion before Easter. PR being undertaken with Bridgwater College.

Phase 2 will then commence Monday 28 April 2003 working from 167 Bath Road to Bower Lane. Duration of phase 2 is three weeks with traffic lights being used where necessary

A38 North Petherton

Mains rehabilitation work along the A38, working from North Petherton towards Bridgwater terminating at Kerland Clinic. Single lane traffic light control will be necessary where minimum width for two way flow cannot be achieved

  Sparrow Hill Way, Weare

Installation of a first time sewerage scheme under a temporary road closure. Scheme originally advertised as commencing Monday 3 March 2003 has been re-programmed to commence 22 April 2003 with a completion date of 15 August 2003. Wessex will be carrying out further consultation with frontagers

  NEW DEVELOPMENT, MIDDLE STREET, PURITON

Construction of foul and surface water sewer works to service new development. Works continue for a further three weeks under aTemporary Road Closure

----------Environment Agency--------

  Nothing to report

----------Cable & Wireless--------

Nothing to report

----------TYCOM--------

Nothing to report

----------TreeFelling--------

Nothing to report

----------SWEB--------

   

Nothing to report

----------BT--------

   

Nothing to report